| Project |
Khudi Hydropower Project Civil Repair Works (Damaged by the Flood) |
| Location |
Lamjung District, Khudi/Ghana Pokhara VDC |
| Owner |
Khudi Hydro Power Ltd. |
| 1st Stage Works |
- Cleaning of the Intake, Gravel Trap, Approach Canal, Settling Basin
- Strengthening of the foundation of Anchor Blocks and Support Piers damaged by flood
- Strengthening of foundation of Retaining wall damaged by the flood
- Opening the buried penstock pipe between anchor blocks and repair damaged section
- Construction of new Anchor blocks, Support piers and Retaining walls
|
| 2nd Stage Works |
- Construction of Retaining wall
- Reconstruction work of the damaged and new Boulder riprap works in Siphon area
- Reconstruction of damaged River Training works
- River Protection Work at required area
- Demolition work of Bid boulders obstructing the flow in the river at Powerhouse area, Landslide area, different location of anchor block and upstream of intake area
- Strengthening works at different areas where flood has scoured and attempted to overtop from the area of anchor blocks
|
| Period of Construction |
From September 26 2008 |