| Project | Dhanusha – Mahottari Transmission Line |
| Tender No | LCB-01/2005 Lot 2 Package A: under Eighth Power Project |
| Employer | Nepal Electricity Authority |
| Works | Construction of 33/11/0.4 kV lines (RE and DSR) and installation of transformers and line accessories at Dhanusha and Mahottari |
| Period of Construction | November 30, 2006 – May 2, 2007 |
Top Third Contractor in Asia for Tunnelling
Himal Hydro is listed as Top Third Contractor in Asia for Tunnelling by Tunnels & Tunnelling International in their Annual Listing 2011. Tunnels & Tunnelling International is the leading news, research, technical information, data and market intelligence resource for the global tunnelling industry.Hydropower Development
- Super Madi Hydroelectric Project (44 MW), Kaski, Nepal
- Middle Modi Hydroelectric Project (15 MW), Kaski, Nepal
Area of Specialization
Other Services